Impact to supply line to Waubaushene TS

Published Date
Thursday, October 7, 2021

Hydro One is performing maintenance on one of the two supply lines from Waubaushene that provides electricity to all NT Power customers in Midland and Tay Township. For the majority of October, electricity will be supplied to all NT Power’s customers in Midland and Tay Township by a single 230kV line. Work is being done to accommodate new breaker bays. Hydro One expects this project to be completed by October 29, 2021.

Should there be a loss of supply during this period, Hydro One has estimated all NT Power’s customers in Midland and Tay Township may be without power for up to 8 hours while service is restored. A pre-outage inspection is being performed by Hydro One crews on the remaining Waubaushene TS to ensure there are no pre-existing issues.