Alert
Unfortunately, we are not able to proceed with your registration if you do not have the power to enter your company into a legally binding agreement with NT Power.
Quaker Hill Phases | Anticipated Start Date | Anticipated Completion Date |
---|---|---|
Phase 1 (Complete) | ||
Phase 2 (Complete) | ||
Phase 3 (Complete--please see note below) | July 2024* | Completed September 30, 2024 |
Phase 4 | April 2025* | August 2025* |
*Weather permitting. |
Phase 3 Property Restoration-- While most restoration work has been completed; any outstanding restoration will be completed once the weather permits. Thank you for your cooperation and support throughout the duration of this project.
NT Power will be retaining a third-party contractor to perform Phase 2-4 work with a planned construction start in September 2023 and proposed completion of all phases by Q3 of 2025, weather permitting.
There will be brief intermittent power interruptions required to complete this work for which you will be notified in advance. If for any reason extended outages are required, extended notification lead time will be given. NT Power will make every effort to reduce the frequency and duration of outages in completing this work.
Upon completion of the work any property or road restoration that is necessary will be completed to “as good or better” condition.
What To Expect
We apologize for any inconvenience this may cause and thank you for your patience and support.
If you have any questions or need more information, please use the form below to contact our operations department.