
Quaker Hill Underground Cable Replacement Project

Project Timelines
Quaker Hill Phases | Anticipated Start Date | Anticipated Completion Date |
---|---|---|
Phase 1 (Complete) | ||
Phase 2 | September 2023 | April 2024* |
Phase 3-4 | March 2024* | October 2024* |
*Weather permitting. |
|
Planned Outages Week of December 11, 2023
Notification will be provided to the listed addresses 48 hours prior to the scheduled outage time.
Monday, December 11, 2023, 8 AM-5 PM
Affected Addresses:
211 |
CURREY CRES |
219 |
CURREY CRES |
217 |
CURREY CRES |
215 |
CURREY CRES |
213 |
CURREY CRES |
218 |
CURREY CRES |
214 |
CURREY CRES |
216 |
CURREY CRES |
212 |
CURREY CRES |
210 |
CURREY CRES |
208 |
CURREY CRES |
206 |
CURREY CRES |
204 |
CURREY CRES |
198 |
CURREY CRES |
202 |
CURREY CRES |
200 |
CURREY CRES |
Tuesday, December 12, 2023, 8 AM - 5 PM
Affected Addresses:
232 |
CURREY CRES |
235 |
CURREY CRES |
233 |
CURREY CRES |
231 |
CURREY CRES |
229 |
CURREY CRES |
230 |
CURREY CRES |
228 |
CURREY CRES |
226 |
CURREY CRES |
227 |
CURREY CRES |
225 |
CURREY CRES |
223 |
CURREY CRES |
221 |
CURREY CRES |
224 |
CURREY CRES |
222 |
CURREY CRES |
220 |
CURREY CRES |
Wednesday, December 13, 2023, 8 AM - 5 PM
Affected addresses:
254 |
CURREY CRES |
256 |
CURREY CRES |
252 |
CURREY CRES |
248 |
CURREY CRES |
246 |
CURREY CRES |
244 |
CURREY CRES |
242 |
CURREY CRES |
250 |
CURREY CRES |
234 |
CURREY CRES |
249 |
CURREY CRES |
241 |
CURREY CRES |
239 |
CURREY CRES |
237 |
CURREY CRES |
240 |
CURREY CRES |
238 |
CURREY CRES |
236 |
CURREY CRES |
Friday, December 14, 2023, 8 AM - 5 PM
Affected addresses:
270 |
WILLIAM ROE BLVD |
277 |
CURREY CRES |
275 |
CURREY CRES |
273 |
CURREY CRES |
280 |
WILLIAM ROE BLVD |
278 |
CURREY CRES |
276 |
CURREY CRES |
274 |
CURREY CRES |
270 |
WILLIAM ROE BLVD |
266 |
CURREY CRES |
272 |
CURREY CRES |
270 |
CURREY CRES |
268 |
CURREY CRES |
264 |
CURREY CRES |
262 |
CURREY CRES |
260 |
CURREY CRES |
258 |
CURREY CRES |
UPDATE: August 2023
NT Power will be retaining a third-party contractor to perform Phase 2-4 work with a planned construction start in September 2023 and proposed completion by Q3 of 2024, weather permitting.
There will be brief intermittent power interruptions required to complete this work for which you will be notified in advance. If for any reason extended outages are required, extended notification lead time will be given. NT Power will make every effort to reduce the frequency and duration of outages in completing this work.
Upon completion of the work any property or road restoration that is necessary will be completed to “as good or better” condition.
What To Expect
- Due to the nature of the work, there will be construction-related noise and dust from the equipment and trucks, though every effort to minimize this will be made.
- Access to the roadway will be maintained.
- Every effort will be made to minimize disruptions as much as possible. When the work is complete, any disturbances to property or roadways will be fully restored to "as good or better" condition.
We apologize for any inconvenience this may cause and thank you in advance for your patience and support.
If you have any questions, or for more information, please reach out to our operations department using the form below.